Top and tailing of offshore jacket

Weight – 385T & 407T

Project scope

To find a custom solution to top and tail the complete fabricated structure and align it with the base jacket structure.

Solution provided

A selection of 3 cranes were used. Our Liebherr 600T crawler crane with 84.0M boom SDBW was used as the main crane, a 400T crawler crane with 64.0M boom and our Liebherr 1200T mobile crane were used as tailing cranes to successfully top and tail the entire structure and then carefully position it over the base structure for welding.